Home » Costs

Costs

Project Cost

Construction cost estimates have been prepared by the School District’s Construction Manager for the proposed improvements at the Elementary School and Jr./Sr. High School and all other project related soft costs have been tabulated and are included in the total project cost figures below.

Total Elementary School Project Cost:   $10,502,402
Total Jr./Sr. High School Project Cost:     $28,440,681

Total Bond Cost:                          $38,943,083

 

Elementary School Cost Estimate

Site Costs: $1,551,600
Construction Costs: $6,986,800
Owner Project Costs: $1,283,899
Owner Contingency: $426,920
Escalation Costs: $253,183

Total Elementary School Project Cost:      $10,502,402

 

Jr./Sr. High School Cost Estimate

Site Costs: $2,688,900
Construction Costs: $21,174,100
Owner Project Costs: $2,926,314
Owner Contingency: $954,520
Escalation Costs: $696,847

Total Jr./Sr. High School Project Cost:      $28,440,681

 

Impact to Taxpayer

The following is a table that shows the projected taxpayer impact on a $39M bond over 30 years.